KUALA LUMPUR: Pengurusan projek pembinaan sekolah antara tempoh 2016 hingga 2021 di bawah Rancangan Malaysia Ke-11 (RMKe-11), termasuk projek sambungan, adalah kurang cekap dan kurang berkesan.
Menurut Laporan Ketua Audit Negara 2021 Siri 1 yang diterbitkan hari ini, terdapat kelemahan di peringkat perancangan, prapelaksanaan dan pelaksanaan projek oleh Kementerian Pendidikan Malaysia (KPM), perunding dan kontraktor.
Selain itu, laporan tersebut menyebut, masalah koordinasi antara kerajaan negeri, pihak berkuasa tempatan (PBT) dan syarikat utiliti, serta isu ketersediaan tapak projek turut menyumbang kepada kemajuan projek.
Situasi tersebut mengakibatkan objektif 87 projek dengan kos RM2.889 bilion untuk menampung lebihan murid melalui pembinaan sekolah baharu, dan ke arah sekolah satu sesi sukar dicapai.
Laporan itu menyebut, antara kelemahan yang perlu diberi perhatian ialah enam projek mengambil masa antara empat tahun dua bulan ke enam tahun dua bulan daripada kelulusan Unit Perancang Ekonomi (UPE) untuk disiapkan.
Katanya lagi, sembilan projek masih dalam tempoh pelaksanaan dan tiga projek belum dilantik kontraktor, walaupun selepas empat hingga 11 tahun diluluskan UPE, selain dua sekolah baharu hanya dibuat setelah bilangan murid melebih 35 orang dalam bilik darjah.
Selain itu, laporan tersebut turut menyentuh mengenai kelemahan perunding dalam reka bentuk lima projek sekolah baharu, menyebabkan kos tambahan sebanyak RM2.16 juta, manakala kelemahan mengenal pasti keperluan di peringkat PBT dan syarikat utiliti bagi enam projek, mengakibatkan peningkatan kos sebanyak RM1.26 juta.
Ketua Audit Negara berkata, terdapat juga pembayaran kepada perunding berjumlah RM1.56 juta bagi empat projek, biarpun kontrak belum dimeterai.
Antara syor yang digariskan dalam laporan tersebut ialah, KPM disaran untuk mengadakan libat urus dengan semua pihak terlibat bagi mengurangkan risiko kelewatan pelaksanaan projek
“KPM hendaklah memastikan tanah yang diserahkan kepada rizab pendidikan oleh pemaju adalah tanah yang sesuai dengan pendidikan, dan tidak memerlukan kerja tanah yang kompleks.
“KPM hendaklah memperkemaskan prosedur dan proses pelaksanaan projek pembinaan sekolah supaya pengurusan lebih teratur, dan mematuhi semua peraturan semasa yang berkuasa,” menurut laporan itu.
Selain itu laporan itu turut menyarankan agar KPM menjalankan kajian semula untuk mengenal pasti keperluan semasa skop pembinaan sekolah bagi projek yang lewat dimulakan pelaksanaannya.
Firdaus Azil
Wed Aug 03 2022
Menurut Laporan Ketua Audit Negara 2021 Siri 1, terdapat kelemahan di peringkat perancangan, prapelaksanaan dan pelaksanaan projek oleh KPM, perunding, dan kontraktor.
Ringgit dibuka tinggi berbanding dolar AS
Pada 9 pagi, ringgit meningkat kepada 4.7065/7100 berbanding dolar AS daripada 4.7080/7100 pada Khamis.
Niaga SPOTLIGHT: Managing healthcare shortages and costs
The Ministry of Health (MOH) received RM41.22 billion under Budget 2024, up from RM36.3 billion the previous year. Personal healthcare expenditures in Malaysia are projected to double to RM13.2 billion by 2028.
However, the national health service faces a severe shortage of medical staff and patient overcrowding, boosting the popularity of private clinics for their convenience and affordability. By 2022, there were over 9,800 registered private health clinics.
Dr. Azizan Abdul Aziz, President of the Malaysian Medical Association (MMA), discusses solutions for public healthcare talent shortages and strategies to maintain affordable private primary care.
However, the national health service faces a severe shortage of medical staff and patient overcrowding, boosting the popularity of private clinics for their convenience and affordability. By 2022, there were over 9,800 registered private health clinics.
Dr. Azizan Abdul Aziz, President of the Malaysian Medical Association (MMA), discusses solutions for public healthcare talent shortages and strategies to maintain affordable private primary care.
AWANI Ringkas: Menjelang PRK DUN Sungai Bakap esok
Ikuti rangkuman berita utama yang menjadi tumpuan sepanjang hari di Astro AWANI menerusi AWANI Ringkas.
PM sampai sumbangan kepada bekas jurutera elektrik hilang punca pendapatan
Perdana Menteri sampai sumbangan kepada Tan Men Heang yang hilang punca pendapatan untuk menyara kehidupannya bersama isteri.
Projek naik taraf 636 loji rawatan kumbahan berada pada tahap 98.5 peratus - SPAN
Status terkini itu hasil langkah segera diambil bersama IWK bagi menangani isu kelewatan serta menyegerakan kemajuan kerja.
UMPSA guna HCI untuk jadi kampus pintar
HCI adalah produk digital yang menggabungkan storan, pengkomputeran, rangkaian dan pengurusan di bawah satu bumbung.
Aplikasi ChatGPT untuk MacOS simpan perbualan tanpa sebarang penyulitan
Mengikut semakan pembangun, OpenAI didapati menyimpan pelbagai data perbualan dan pertanyaan dalam teks biasa, tanpa sebarang penyulitan.
Bantuan kemanusiaan Arab Saudi di Gaza terjejas akibat penutupan Rafah
Makanan yang ada di dalam ratusan trak yang menunggu memasuki Gaza dan disimpan di gudang dijangka mendekati tempoh tamat.
Sheikh Al-Azhar tamatkan lawatan khas di Malaysia
Sheikh Al-Azhar hari ini menamatkan lawatan khas empat hari ke Malaysia atas undangan Perdana Menteri, Datuk Seri Anwar Ibrahim.
Prof Said Bani individu pertama dari Malaysia raih anugerah ‘Communicator of The Year’ IABC Asia Pasifik
Bani catat sejarah pengamal komunikasi pertama Malaysia terima anugerah 'Communicator of The Year' IABC Asia Pasifik dalam kategori Senior Communication Professional.
Laporan audit: Pengurusan projek sekolah baharu bernilai RM2.889 bilion kurang cekap
Terdapat kelemahan di peringkat perancangan, prapelaksanaan dan pelaksanaan projek oleh KPM, perunding, dan kontraktor.